TL;DR: Start 4–6 months out. Line up fit-out, cabling, IT and movers in that order, and plan reinstatement of the old unit. Update your registered office address with ACRA within 14 days of the change, or face late lodgment penalties.
An office move touches almost every supplier you have: landlord, fit-out contractor, IT, telecoms, furniture, cleaners and movers. Most delays come from the long-lead items such as building approvals, internet circuits and custom joinery, so the order of work matters more than any single quote. This page gives a timeline, the providers involved and the filings that follow.
“They must report these changes via Bizfile within 14 days to avoid penalties.”
— ACRA, Updating company information, officers & shareholders (quoted verbatim, checked 31 October 2026)
Checklist: what to do, in order
- Confirm space and lease. Headcount plan for 2–3 years, lease term, reinstatement obligations and fit-out period.
- Brief fit-out contractors. Layout, meeting rooms, M&E works and building management approvals.
- Order network and internet early. Fibre circuits and structured cabling have long lead times.
- Plan IT migration. Servers, Wi-Fi, printers, access control and a cut-over weekend.
- Furniture and workstations. Order early if custom or imported.
- Book movers. Survey, packing plan, insurance and lift bookings at both buildings.
- Reinstate the old unit. Agree reinstatement scope with the old landlord and get quotes.
- Update addresses. ACRA registered office within 14 days, plus IRAS, banks, insurers, website and invoices.
- Post-move snagging. Defects list with the contractor and IT checks in the first week.
Which providers you need, and when
Most Singapore companies handle this event with a few outside providers brought in at different stages. The table shows the usual order. Each provider type links to a page where you can compare options and get matched for free.
| When | Provider type | What they do |
|---|---|---|
| 4–6 months before | Office renovation contractor | Design, approvals, fit-out |
| 3–4 months before | Network cabling contractors | Structured cabling and fibre |
| 2–3 months before | Office furniture suppliers | Workstations, chairs, storage |
| 1–2 months before | Managed IT services | IT migration, Wi-Fi, security |
| Move week | Office movers | Packing, transport, set-up |
| After move | Office cleaning | Post-renovation and regular cleaning |
What it costs
Official figures link to their source. Provider fees are indicative estimates from typical Singapore quotes; your quote will depend on scope, so ask for an itemised proposal.
| Item | Figure | Source |
|---|---|---|
| ACRA late lodgment penalty (address not updated in time) | S$50 within 3 months; S$200 after | [1] |
| Office fit-out (mid-range) | S$60 – S$150 per sq ft | Indicative estimate (FYAdvisers planning estimate from typical Singapore quotes; confirm with providers) |
| Reinstatement of old unit | S$10 – S$30 per sq ft | Indicative estimate (FYAdvisers planning estimate from typical Singapore quotes; confirm with providers) |
| Office move (20–50 staff) | S$2,000 – S$8,000 | Indicative estimate (FYAdvisers planning estimate from typical Singapore quotes; confirm with providers) |
| Structured cabling | S$150 – S$300 per data point | Indicative estimate (FYAdvisers planning estimate from typical Singapore quotes; confirm with providers) |
Official rules and where to check them
| Agency | Rule | Official page |
|---|---|---|
| ACRA | Changes to company information, including the registered office address, must be reported via Bizfile within 14 days. | ACRA: Updating company information, officers & shareholders |
| ACRA | Late lodgment penalties apply to filing due dates from 9 December 2024: S$50 within three months and S$200 after. | ACRA: Late lodgment penalties |
This page summarises official guidance for planning purposes. It isn't legal, tax or financial advice. Rules change, so check the linked official pages before you act.
Related providers and tools
Need help with this? Tell us what's happening and our concierge will introduce 1 to 5 vetted providers, free. Use the form or WhatsApp us on +65 9071 3976.
Sources
All business events · How we vet providers
Frequently asked questions
How far ahead should I plan an office move in Singapore?
Four to six months is typical for a fitted move of 20 or more staff. Building approvals, internet circuits and custom furniture are the usual long-lead items.
Do I need to tell ACRA when my office moves?
Yes, if it is your registered office address. ACRA requires changes to company information to be reported through Bizfile within 14 days.
What is reinstatement?
Returning the old unit to the condition the lease requires, often bare shell. It can be a large cost, so check the lease and get quotes early.
Should one contractor do everything?
A design-and-build fit-out contractor can manage most trades, but IT, cabling and movers are often contracted separately. Ask who coordinates the cut-over weekend.