In short: Industrial renovations fail when a platform, a heavy machine or a new use is added without checking floor loading, planning use and fire safety. BCA’s insignificant-works list is narrow for platforms. B1 and B2 rules are on a separate page. JTC units also follow JTC’s steps. Checked 12 Nov 2026.
Use class and change of use on the B1 and B2 page. If the landlord is JTC, follow the JTC steps as well. This list is the physical checks.
Ten checks
1. Confirm the lawful use
B1, B2 and any URA change of use are already explained on that property page. Do not restart the explanation here. If the activity is not what the unit is approved for, stop and use that page before you draw partitions.
2. Get landlord or JTC consent for hacking, anchoring, roof plant and partitions
JTC’s guidelines treat those as works that need endorsement. A private industrial landlord can be just as specific. Written consent comes before the drill.
3. Compare floor loading with the machine or the racking
If the load may rise, ask a civil professional engineer. HDB’s shop guide uses a professional engineer when a new use increases imposed load. That is an HDB example, not a rule imported onto every factory. The principle to copy is: do not guess a slab.
4. Read the storage-platform limits before you call a mezzanine “just racking”
The First Schedule, from 1 April 2025, includes a single-level platform used solely for storage of goods, in an industrial building, not accessible to the public, only within stated limits: height not more than 4 m, area not more than 50 m², beam or slab spans not more than 6 m, and cantilevers not more than 3 m, with access stairs under the related item. An office, a production floor or a retail mezzanine is outside that item. A larger platform is outside it. Other authorities may still apply. A qualified person confirms the reading. The statute text is the First Schedule.
5. Treat an “ancillary office” as both a partition question and a fire question
Lightweight partition conditions are on the permits checklist. SCDF’s minor-addition schedule allows only limited ancillary office or store uses, and not where occupancy load increases. See the fire-safety list.
6. Ask about compartments and hose reels when you add rooms or high storage
New rooms and tall storage can change escape and fire-fighting access. Point the qualified person at SCDF plan approval. This page does not invent Fire Code travel distances.
7. Separate ventilation from a retail kitchen
Extraction for a process is a consultant’s question. JTC lists NEA as one authority that may apply. If the activity is actually a food shop, use the F&B list. Do not mix the two checklists because both involve a hood.
8. Work at height is a safety permit, not an occupation permit
MOM’s 2014 factsheet says a permit-to-work is generally required where a person may fall more than 3 metres, unless fall risks are mitigated by adequate edge protection. Racks, mezzanines and roofs are where that question appears. It does not replace a fire safety certificate.
9. Drainage and chemicals: ask, do not invent a licence name
If the process stores chemicals or discharges trade effluent, ask the consultant which agency applies. JTC names NEA as a possible authority. This pack does not extract a chemical-storage licence, so this page will not name one.
10. A platform that is already over the cap
Illustrative only. A 60 m² storage platform is outside the 50 m² First Schedule area. Calling it racking does not change the area. This page does not invent an enforcement outcome.
Factories: renovation for manufacturing. Warehouses: renovation for logistics.
WhatsApp +65 9071 3976 (chat).
Frequently asked questions
Is a storage mezzanine always exempt from BCA plans?
No. The First Schedule, as amended from 1 April 2025, allows a single-level storage platform in an industrial building only if every stated limit is met, including height, area and spans, and the platform is not accessible to the public. Other authorities may still apply. A qualified person confirms it.
Does this apply only to JTC units?
No. Use and structure questions apply more widely. JTC adds its own consent steps, which are on the JTC list.
Can I turn a corner of the warehouse into a shop?
That is a use question. Start with the B1 and B2 page and URA. Do not treat a partition as a change of use.