In short: JTC’s public page says all fitting-out or renovation works, temporary or permanent, need approval from JTC and the relevant authorities before work starts. The sequence is plan consent, other authorities, facilities-management clearance, the works, then completion documents. A handbook exemption list can apply to JTC consent only. Checked 12 Nov 2026.
Use zoning on the B1 and B2 change-of-use page. Use physical checks on the warehouse and factory list. This page is JTC’s own sequence, from fitting-out and renovation works, checked 12 November 2026.
What to do, in JTC’s order
1. Read the overview and the handbook together
The overview says all fitting-out or renovation works, temporary or permanent, need approval by JTC and the relevant authorities before works commence. The space submission handbook tells tenants to check whether works are exempted from JTC plan consent under List A. Even if JTC consent is not required, other authorities may still be. Do not flatten those two documents into “everything minor is exempt” or “nothing is ever exempt”.
2. Step 1: plan consent
Engage a professional engineer, registered architect or qualified person and apply for JTC’s consent. The page says pre-consultation is highly recommended for Punggol Digital District and for Jurong Innovation District sites it names: CleanTech Park, Bulim, Bahar and Tengah.
3. Step 2: other authorities after JTC consent
JTC lists URA, FSSD and NEA as examples. The consultant advises which apply. Building and fire tests are the permits checklist and the fire-safety list.
4. Step 3: facilities management and a permit to work before anyone arrives
Check whether you must use the building’s appointed contractor. Raise a request to start with the facilities-management company. The page describes an electronic permit-to-work account, risk assessment and method statement, worker lists, work-at-height certificates where relevant, and JTC’s consent letter. It says assessment typically takes less than 20 days from the date of submission to the final decision. That is JTC’s stated typical window. It is not a promise for your file.
5. Step 4: rules on site
Noisy or disruptive works only after working hours. No weekend or public-holiday works without prior JTC approval. Stay inside the unit. Protect common areas. Joint inspections before and after. The tenant or contractor bears repairs or cleaning of common areas.
6. Step 5: completion documents
JTC says the consultant must apply for a temporary occupation permit and/or a certificate of statutory completion with the relevant authorities before you move in, then submit a complete set to JTC within one month. That step applies where those certificates are required for the works. It is not an automatic rule for a furniture-only refresh with no building works. Ask the qualified person which certificates this job needs.
7. Treat the CORENET fee waiver as temporary
The page states that the application processing fee is temporarily waived for documents submitted through CORENET. Label it temporary. Re-check JTC before you rely on a zero fee.
8. Loading, roof plant and structure still need endorsement
JTC’s fitting-out guidelines treat heavy machinery, roof equipment, hacking or drilling into structure, and new partitions as items that need endorsement. The physical tests are the warehouse list. A storage platform that hopes to sit inside BCA’s insignificant-works limits has tight size caps. Do not assume a mezzanine is “just racking”.
9. Two jobs, two consent questions
Illustrative only. Lightweight partitions and a small ancillary office are not the same file as a storage platform. The first still needs the overview-versus-List-A question. The second is likely outside BCA’s storage-platform exemption if it exceeds the limits on the warehouse list. This page adds no consent time beyond JTC’s “typically less than 20 days” for the facilities-management assessment.
Matching for factories is renovation for manufacturing. Matching for warehouses is renovation for logistics.
WhatsApp +65 9071 3976 (chat).
Frequently asked questions
Do I need JTC approval for internal partitions?
JTC’s overview, checked 12 November 2026, says all fitting-out works need approval before commencement. The space submission handbook also tells tenants to check a List A of works exempted from JTC plan consent. Other authorities may still apply. Ask JTC or your qualified person. Do not exempt yourself.
Can we work on Sunday to finish faster?
Not without JTC’s prior approval. The public page says no weekend or public-holiday works without that approval, and noisy or disruptive works only after working hours.
Does JTC require bizSAFE?
The pages checked do not state bizSAFE as a JTC statutory licence. The start-work request does list risk assessments, method statements and work-at-height certificates where relevant. A landlord or facilities manager may still ask for bizSAFE in a contract.