In short: A low headline is often a short scope. Put quotes on the same floor plan and the same inclusions before you compare them. Published benchmarks stay on the existing cost guide. This page is only about gaps in the paper. Checked 12 Nov 2026.
Published fit-out benchmarks live on the office renovation cost guide. The calculator applies those benchmarks to an area. This page does not add a price. It lists lines that disappear between bids.
Twelve lines to look for
1. Landlord, qualified person and authority fees
Ask who pays and who files. A quote that is silent has not included them. The map is the permits checklist.
2. Sprinklers, detectors and emergency lighting
These are often a provisional sum, and they can change the SCDF path. See the fire-safety list. If the line is missing, the bids are not comparable.
3. Air-conditioning changes and after-hours access to condensers
Moving a cassette or a duct is not “included in the ceiling” unless the quote says so. Buildings often restrict when condensers can be reached. Air-conditioning servicing is a different contract from the fit-out. Say which one you are buying.
4. Data, racks, Wi-Fi and AV
These are frequently a separate IT vendor. Write that down, or put them in the builder’s scope. Silence means you will buy them later, at a date the programme did not hold.
5. Furniture
Workstations, chairs and a reception desk are often outside the builder’s number. Office furniture suppliers are a separate match. Either route is fine if the quote says which.
6. Pantry appliances and plumbing
A sink, a filter and a fridge are small on a drawing and easy to omit. Ask whether water, waste and the appliance itself are in the price.
7. Hoarding, after-hours labour, escorts and the loading bay
These come from the landlord guide, not from a brochure. If the building only allows noisy work at night, a daytime rate is the wrong comparison.
8. Making good, lift protection and debris
Common-area damage and rubbish removal should be a line. “Site will be left tidy” is not a method.
9. Provisional sums and star items
If a line says “omitted if not required”, it must still be listed, with what would trigger it. A silent exclusion cannot be compared.
10. GST, variation rates and the payment schedule
Ask whether the number includes GST. Ask how a change is instructed and priced. Do not invent a deposit percentage. The contract checklist is where those clauses go.
11. As-builts, manuals, warranties and defects
Handover is a pack of documents, not only keys. If defects liability is absent, ask for it. There is no official length in this pack.
12. Reinstatement at the end of the lease
A fit-out bid rarely prices the strip-out you will owe later. Raise it now. The cost benchmarks for reinstatement stay on the reinstatement cost page. The process mistakes are a separate list.
How to compare three quotes
| Quote A | Quote B | Quote C | |
|---|---|---|---|
| Same floor plan? | |||
| Exclusions written? | |||
| Provisional sums listed? | |||
| Programme against your access date? | |||
| Who files landlord and authority papers? |
Leave the price column off until those five rows match. Illustrative only: a bid that omits sprinkler shifts and furniture will look cheaper than a design-and-build bid that includes both. The gap is scope, not a bargain.
WhatsApp +65 9071 3976 (chat).
Frequently asked questions
Why is a renovation quote much lower than the cost guide?
The cost guide cites published 2026 benchmarks. It is not a quote for your floor. The usual gap is scope. Compare inclusions before you compare totals.
Should furniture be in the same contract?
Either is workable if it is written down. Many buyers split furniture from the builder. This page does not claim one route is better value.
Is there an official cap on variation rates?
No official standard rate was found in the sources for this pack. Put the variation rule in the contract. The payment and variations listicle is that checklist.