# Office fit-out contracts in Singapore: payment, variations and defects to insist on

> What to put in an office fit-out contract: milestones, variations, retention and defects. No official deposit percentage. Checked 12 Nov 2026.

Source: https://www.fyadvisers.com/blog/office-fit-out-contract-payment-variations-singapore/  
Author: Fiona Wang, FYAdvisers  
Published: 2026-11-12  
Last updated: 2026-11-12

Engagement-letter themes and any fee bands already published sit on [how to choose a contractor](/blog/how-to-choose-commercial-office-renovation-contractor-singapore/). This list goes further into payment and change. It does not reprint that fee table.

## Twelve clauses to lock

### 1. Attach the drawings the price was based on

If the contract does not include the same plans and specification as the quote, you cannot later point at a missing line. Start from the [exclusions list](/blog/items-often-missing-office-fit-out-quotes-singapore/).

### 2. Tie payment to milestones

Name the events: design sign-off, landlord approval, building services complete, practical completion. “Progress” without a test is not a milestone. This page does not prescribe percentages.

### 3. Do not import a “normal” deposit

There is no official commercial deposit in this pack. Negotiate it. [CaseTrust’s renovation scheme](https://www.case.org.sg/casetrust/casetrust-accreditation-for-renovation-businesses/), checked 12 November 2026, discusses homeowner prepayment protection. It is not the default for an office contract.

### 4. Say whether any sum is held back, and when it is released

Retention means a held amount until stated defects are cleared. Describe that idea in the contract if you want it. Do not copy a percentage from a consumer guide. None is official here.

### 5. Variations only in writing, priced before the work

Who may instruct. Whether a rate is already agreed. A text message that says “go ahead” without a price is how week six becomes a dispute. The route you chose, design-and-build or tender, does not remove this clause. See [design-and-build versus tender](/blog/design-and-build-vs-designer-tender-office-fit-out/).

### 6. Separate the contractor’s delay from the landlord’s or an authority’s delay

Write what happens to time in each case. Do not invent a liquidated-damages rate. If the lease has one, that number is in your lease, not in this article.

### 7. Define “complete”

Practical completion, a fire safety certificate where fire safety works were done, and furniture install are three different dates. The [fire-safety list](/blog/scdf-fire-safety-office-fit-out-maa-fsc/) and the [timeline](/blog/office-fit-out-timeline-steps-singapore/) keep them apart. The contract should too.

### 8. Make insurance, safety documents and licensed trades a condition of starting

No mobilisation until the certificates the landlord asked for are in hand, and electrical, gas and water work is with the licensed trade the job needs.

### 9. State a defects period without pretending it is customary

The how-to-choose guide may already discuss defects. If you name a number of months, label it as the period in the contract you are signing, or mark an example as illustrative. This pack does not contain an official defects period.

### 10. Say how the contract ends, and who owns the drawings

Termination, who finishes remaining work, and whether you may give the drawings to another firm. Ask before you need the answer.

### 11. If the contractor touches landlord services, say who repairs them

Sprinkler mains and base-building air-conditioning are the landlord’s system. The contract should say who makes them good. Reinstatement of the whole unit is a later job: [reinstatement mistakes](/blog/office-reinstatement-mistakes-lease-end-singapore/).

### 12. A verbal extra, unpriced

**Illustrative only.** In week six someone says “just add two rooms”. The invoice arrives without a rate. A written variation, priced first, is the control. This page does not attach a dollar figure to those rooms.

Lease wording is for a [commercial lease lawyer](/find/corporate-lawyers/commercial-lease-lawyer-singapore/) if you need advice. FYAdvisers does not draft your fit-out contract and is not a law firm. Law practices pay FYAdvisers nothing.

WhatsApp +65 9071 3976 ([chat](https://wa.me/6590713976)).

## Frequently asked questions

### What deposit should I pay?

No official figure is in the sources for this pack. Negotiate it against cash flow and the landlord’s rules. CaseTrust prepayment protection, checked 12 November 2026, is written for homeowners. It is not the commercial default.

### Does a small change need a written variation?

If it changes price or time, write it down before the work proceeds, with a price or a stated rate. That is a process recommendation, not a legal opinion. FYAdvisers is not a law firm.

### Where do I get firms to bid?

Through the office renovation matching page. This article does not name contractors.
