# HDB shop or office renovation in Singapore: a permits and working-hours checklist

> HDB shop and office renovation: QP, CORENET, the contractor directory, notice of alteration and published hours. Checked 12 Nov 2026.

Source: https://www.fyadvisers.com/blog/hdb-shop-renovation-permits-checklist-singapore/  
Author: Fiona Wang, FYAdvisers  
Published: 2026-11-12  
Last updated: 2026-11-12

This list follows HDB’s [December 2025 renovation guide for shop tenants and owners](https://www.hdb.gov.sg/-/media/shops-and-offices/managing-an-hdb-shop-or-office/renovation/Renovation-Guide-for-shop-tenant-and-owner-Dec-2025R2.pdf) and the [addition and alteration page](https://www.hdb.gov.sg/shops-and-offices/managing-an-hdb-shop-or-office/renovation/addition-alteration-aa-works), both checked 12 November 2026. HDB says the guide is current at issuance and can change. It does not override your tenancy. It is not the rulebook for a private mall.

## Twelve checks before works start

### 1. Get HDB’s prior approval

The guide says prior approval is required before fitting-out. Read it with the tenancy or memorandum of lease. A contractor’s start date is not that approval.

### 2. Have a qualified person submit on CORENET

Applications must be made by a registered architect or professional engineer. The guide says no works until approvals and clearances are obtained, and that those clearances are furnished to HDB for record. Appoint the qualified person to submit via CORENET and obtain clearances from HDB, BCA and FSSD before works start.

### 3. Use a contractor on HDB’s directory and check InfoWEB

The guide tells tenants and owners to engage licensed contractors listed in the HDB Directory of Renovation Contractors and to check registration on HDB InfoWEB. A standalone directory URL used for flats returned 404 on 12 November 2026. Follow the live InfoWEB check named in the guide. HDB is not a party to your private contract. The guide says disputes sit between the parties.

### 4. Keep to the published hours

General renovation: 9am to 6pm, Monday to Saturday. No works on Sunday and public holidays. Noisy works, including demolition, removing finishes, cutting tiles and excessive drilling or hammering: 9am to 5pm, Monday to Friday only. Not weekends, public holidays, or the eves of major public holidays. The guide lists New Year’s Day, Chinese New Year, Deepavali, Hari Raya Puasa and Christmas Day.

### 5. Display a notice of alteration for the whole job

Apply at the form HDB publishes, linked from the guide as go.gov.sg/hdb-noa-application. The guide says even minor works, including laying floor or wall finishes, shelves or racks, and replacing doors or windows, need a notice of alteration before starting.

### 6. Know lodgement, addition and alteration, and the exemption list

On the addition and alteration page, lodgement would likely take 7 working days for approval, subject to review. Addition-and-alteration applications would likely take 14 working days, subject to review. The same page has an exemption list: some items need no HDB planning-group clearance if the conditions are met. Read that live list. This article does not retype it from memory. The page also notes floor-finish thickness and load limits for some works. Quote the current wording when you brief the qualified person.

### 7. Treat a change of use as its own HDB step

Obtain HDB in-principle change-of-use approval. If the new use has a higher imposed load, appoint a civil professional engineer for structural adequacy. The guide’s example is office to gym, fitness or institution. If the existing and proposed uses fall under different SCDF fire-code purpose groups, seek SCDF clearance. The guide’s example is a minimart versus a music school. Fire safety generally is the [SCDF list](/blog/scdf-fire-safety-office-fit-out-maa-fsc/).

### 8. Use licensed trades and open utility accounts

Water: a PUB-licensed water service plumber. Gas and electrical: EMA-licensed workers. The guide says to open utility accounts before starting.

### 9. Read what HDB says is not allowed

Overloading or hacking beams, columns or other structural members. Façade or reinforced-concrete works that affect public safety. Converting living quarters without approval. Flickering illuminated signboards. Fire-safety violations. The guide also says a shop owner or tenant can face a fine of up to $10,000 and/or jail of up to one year if a window falls due to lack of maintenance. That is the guide’s wording about maintenance, not a FYAdvisers penalty.

### 10. Plan debris, hoarding and who may demolish

The guide covers debris removed daily, hoarding, skip tanks, protective equipment, and demolition workers certified as the guide specifies. Works stay inside the unit. Do not treat the corridor as a store.

### 11. Give exhaust the clearance the guide states

For mechanical ventilation, hoods and ducts shall have 500 mm clearance from unprotected combustible materials, with access panels. If the unit will be a food shop, add the [F&B mistakes list](/blog/fnb-renovation-mistakes-singapore/) and SFA’s layout rules. Do not stop at HDB’s clearance figure.

### 12. Keep signage on the signage page

Shopfront and outdoor signs are the [signage licence guide](/signage/signage-licence/). Retail comparisons across mall, shophouse and HDB are the [retail checklist](/blog/retail-shop-fit-out-checklist-singapore/). The wider map is the [permits checklist](/blog/commercial-fit-out-permits-approvals-singapore/).

HDB publishes its own enquiry route on its pages. Use that for HDB questions. Matching questions to FYAdvisers use the number at the end of this article only.

WhatsApp +65 9071 3976 ([chat](https://wa.me/6590713976)).

## Frequently asked questions

### Can I use my usual private-office contractor?

Only if they are on the HDB Directory of Renovation Contractors and you have checked the live InfoWEB listing, as HDB’s December 2025 shop and office guide requires. A private-office track record is not that check.

### Can we hack on Saturday?

On that December 2025 guide, noisy works such as demolition, removing finishes, cutting tiles and excessive drilling are 9am to 5pm, Monday to Friday only. Not weekends, public holidays, or the eves of the major public holidays the guide lists.

### Is the contractor directory only for HDB flats?

The flat directory is a residential product. HDB’s own December 2025 shop and office guide also tells commercial tenants and owners to use registered renovation contractors and to check InfoWEB. Do not mix flat-renovation consumer schemes with this page.

### How long does HDB take to approve?

HDB’s addition and alteration page, checked 12 November 2026, says lodgement would likely take 7 working days for approval, subject to review, and addition-and-alteration applications would likely take 14 working days, subject to review. Those are not guarantees.
