# Commercial fit-out permits in Singapore: a 12-point approvals checklist

> A 12-point checklist of landlord, BCA, SCDF, URA, HDB and JTC approvals a commercial fit-out may need. Checked 12 Nov 2026. Not a QP opinion.

Source: https://www.fyadvisers.com/blog/commercial-fit-out-permits-approvals-singapore/  
Author: Fiona Wang, FYAdvisers  
Published: 2026-11-12  
Last updated: 2026-11-12

A fit-out can need several consents at once. Missing one of them is how a start date slips. This list is a map of what to ask. It is not a ruling on your drawings.

## Twelve approvals to check

### 1. Start with the lease and the building

Most office and mall leases, and many strata by-laws, require written landlord or management-corporation consent before works start. They often also set a fit-out deposit, insurance, working hours and which M&E contractors may touch base-building systems. That is a contract, not a government licence. Unpack it with the [landlord and MCST checklist](/blog/landlord-mcst-fit-out-guidelines-checklist-singapore/).

### 2. Appoint a qualified person to choose the submission path

A registered architect or professional engineer prepares building and fire submissions. Do not treat a contractor’s “we have done this before” as a substitute for that judgement. FYAdvisers does not act as a qualified person.

### 3. Ask whether BCA plan approval is required

[BCA’s page on building works not requiring approval](https://www1.bca.gov.sg/guidelines-and-requirements/building-works-not-requiring-approval/), checked 12 November 2026, says insignificant building works do not need a BCA plan submission. Owners must still observe safety and obtain approvals from other authorities, and should consult a qualified person when unsure. Unauthorised addition and alteration can be an offence under the Building Control Act.

The [First Schedule of the Building Control Regulations 2003](https://sso.agc.gov.sg/SL/BCA1989-S666-2003?ProvIds=Sc1-), read on Singapore Statutes Online as the current version on 12 November 2026, defines those works. Items that can matter in an office, each with conditions, include openings in or demolition and reinstatement of non-load-bearing walls, replacement of existing floor and wall finishes, certain lightweight suspended false ceilings, partitions, and air-conditioning works. The partition item, in buildings other than landed houses, is limited to lightweight material as the Schedule defines it, and to a stated height. Masonry or other non-lightweight partitions in a commercial unit sit outside that exemption. Deciding what is load-bearing is an engineering judgement. A BCA exemption does not remove SCDF, URA or the landlord.

### 4. Run SCDF as a separate test

Layout changes that affect escape routes, fire compartments or fire protection, and some changes of use, are fire safety works. Some minor works can be lodged instead of a full plan. Occupying after fire safety works needs a fire safety certificate, or sometimes a temporary fire permit. The detail is the [SCDF decision list](/blog/scdf-fire-safety-office-fit-out-maa-fsc/).

### 5. Check whether the activity still matches the approved use

[URA’s change-of-use page](https://www.ura.gov.sg/guidelines/property-and-business-owners/business-owners/change-use-of-property-for-business/), last updated on the page as 12 November 2026 when checked that day, states an application fee of $500. Fees are collected to process the case and are non-refundable. URA says it takes 10 working days to assess an application, and more time if the submission is incomplete or other agencies must be consulted. Apply via GoBusiness.

Some changes to shop use in commercial buildings do not need a fresh planning permission. [URA’s authorisation page for conversions to shops](https://www.ura.gov.sg/guidelines/property-and-business-owners/business-owners/change-use-of-property-for-business/related/authorisation-conditions-conversions/), last updated 23 June 2026 and re-opened for this article on 12 November 2026, lists uses that can change to a shop without planning permission, including office, restaurant, showroom and others, and sets conditions: the premises were previously approved for commercial use and computed as commercial gross floor area; the development is not subject to special planning conditions on allowable use; the change is for an individual unit, not an en-bloc conversion; and licensing requirements of other agencies are met before the use starts. Party-walled shophouses and shopflats are excluded from one of the authorisations. Read the live page. Do not assume your unit is on the list.

[URA’s restaurant criteria](https://www.ura.gov.sg/guidelines/property-and-business-owners/business-owners/change-use-of-property-for-business/related/criteria-for-restaurant/), also last updated 23 June 2026 and re-opened the same day, say planning permission is not required for a new restaurant in shopping centres and commercial buildings, and that shophouse applications outside stated areas are assessed individually. Eating-establishment mistakes are on the [F&B list](/blog/fnb-renovation-mistakes-singapore/).

### 6. If the unit is an HDB shop or office, use that path

Prior HDB approval, a qualified person on CORENET, a contractor on HDB’s directory, a notice of alteration, and published working hours. The [HDB shop checklist](/blog/hdb-shop-renovation-permits-checklist-singapore/) is the list. Do not apply private-mall hours to an HDB unit.

### 7. If the unit is JTC’s, get JTC consent before you start

JTC’s public page says fitting-out works need JTC and the relevant authorities before commencement. The [JTC steps](/blog/jtc-industrial-fit-out-approval-steps/) are the sequence, including the facilities-management clearance to mobilise.

### 8. Treat outdoor signage as its own licence

A shopfront or illuminated sign that faces outdoors can need a BCA outdoor advertising sign or signboard licence. The rules are on the [signage licence guide](/signage/signage-licence/). This page does not restate them.

### 9. Keep electrical, gas and water work with licensed trades

HDB’s December 2025 shop and office guide tells tenants to use a PUB-licensed water service plumber and EMA-licensed workers for gas and electrical work. Ask for the same evidence in a private building. “The carpenter will handle the power” is not a submission.

### 10. Separate workplace safety from an occupation permit

[MOM’s work-at-heights factsheet](https://www.mom.gov.sg/-/media/mom/documents/safety-health/factsheet-on-wahamendmentregulations.pdf) says a permit-to-work is generally required where a person may fall more than 3 metres, unless fall risks have been mitigated through adequate edge protection. That is workplace safety law. It is not a fire safety certificate. [bizSAFE](https://www.tal.sg/wshc/programmes/bizsafe/about-bizsafe), checked 12 November 2026, is a WSH Council programme. Level 3 and above recognises risk-management systems. Landlords often ask for it in a contract. It is not, by itself, a statutory fit-out licence.

### 11. Keep one approvals log

Record what was submitted, who consented, any fire certificate numbers, and the as-built drawings. Landlords ask for this at the end. The [timeline](/blog/office-fit-out-timeline-steps-singapore/) is the sequence. [Reinstatement mistakes](/blog/office-reinstatement-mistakes-lease-end-singapore/) are what happens if the file is missing.

### 12. Do not turn this into a promised number of weeks

**Illustrative only.** An SME office that moves lightweight partitions and adds a pantry is a different approvals path from a shop converting to a restaurant. The first may still need the landlord and a qualified person’s view of SCDF. The second is likely to involve use, kitchen rules and fire safety. Neither path has an official duration on this page.

Contractor choice, including what CRS does and does not require, stays on the [how to choose a contractor](/blog/how-to-choose-commercial-office-renovation-contractor-singapore/) guide and the [CR06 register](/contractors/cr06-interior-decoration-and-finishing-works/). CRS, on [BCA’s page](https://www1.bca.gov.sg/growth-and-transformation/procurement/registration-of-built-environment-firms/contractors-registration-system-crs/) last updated 10 September 2026, is a registry. Since 1 June 2025, firms that wish to hire construction S Pass or Work Permit holders must register. Registration is also required for public-sector construction tenders. It is not a general licence for every private fit-out. [BCA registration consultants](/find/bca-registration-consultants/) are a matching page for firms that need help with that registry.

WhatsApp +65 9071 3976 ([chat](https://wa.me/6590713976)).

## Frequently asked questions

### Do I need a BCA permit for office renovation in Singapore?

Only if the works are not insignificant building works under the First Schedule of the Building Control Regulations. A qualified person should decide. Other approvals, including the landlord and SCDF, may still apply. Checked 12 November 2026.

### If BCA says the works are insignificant, do I still need a fire safety certificate?

BCA and SCDF run different tests. Insignificant works waive BCA plan submission, not automatically SCDF duties. The fire-safety listicle walks through plan approval, minor addition and alteration lodgement, and the fire safety certificate.

### How much is a URA change-of-use application?

URA’s change-of-use page, checked 12 November 2026, states a fee of $500. The fee is collected to process the case and is non-refundable. URA says it generally takes 10 working days, and longer if the submission is incomplete or other agencies must be consulted.

### Who submits the plans?

A qualified person, usually a registered architect or professional engineer, prepares BCA and SCDF submissions. FYAdvisers does not submit plans and is not a qualified person.

### What about an HDB shop?

HDB shops and offices have their own CORENET, contractor-directory and working-hour rules. Use the HDB shop checklist. Do not copy private-mall or flat-renovation rules onto an HDB commercial unit.